https://mediawiki.middlebury.edu/PieMatrix/index.php?title=Duration_in_Templates_and_how_it_effects_Live_Projects&feed=atom&action=historyDuration in Templates and how it effects Live Projects - Revision history2024-03-29T00:28:27ZRevision history for this page on the wikiMediaWiki 1.35.14https://mediawiki.middlebury.edu/PieMatrix/index.php?title=Duration_in_Templates_and_how_it_effects_Live_Projects&diff=126&oldid=prevCorinna Noelke: Created page with "*If you update duration in a template for future use, it will not dynamically update any steps that have dates or are either marked in progress or completed. This is a feature..."2014-12-05T17:03:53Z<p>Created page with "*If you update duration in a template for future use, it will not dynamically update any steps that have dates or are either marked in progress or completed. This is a feature..."</p>
<p><b>New page</b></p><div>*If you update duration in a template for future use, it will not dynamically update any steps that have dates or are either marked in progress or completed. This is a feature to prevent any unwanted changes once the work has begun. Dynamic updates only change the not-started steps.<br />
*The duration on a layer is considered more of a “hint” from a schedule perspective, and subject to being overruled as the project develops. So, if the step has dates, a duration set by hand, or progress (In Progress or Completed) the duration in the project will not update when changed in the template.</div>Corinna Noelke